343 WEST 400 SOUTH
SALT LAKE CITY, UT 84101

866.679.MUDD

FLOWABLE FILL

Concrete is one of the most versatile materials on the planet, and there is no better demonstration of its versatility than flowable fill.

MURDOCK CANAL
Location: Orem, Utah to Lehi, Utah

Project Size/Scope: 89,101 total yards of flowable fill

Project Description:
Every day over a 12-month period, Metro Ready Mix had 8–10 trucks onsite servicing the Murdock Canal project and ensuring the fast-pace delivery of flowable materials, without interruption. Metro averaged approximately 800 yards per day. This massive project was completed a year ahead of schedule in part due to Metro’s speed and efficiency.

Murdock Canal Project
Murdock Canal Project
Murdock Canal Project
Murdock Canal Project

Metro Ready Mix greatly exceeded our expectations. The Murdock Canal project was very time-sensitive, and Metro assisted in completing the project a year ahead of schedule. Their work on this project shows that Metro will do whatever it takes to get a job done well."

Drew Downs, Ames Construction